Decision on Conducting an Interim Review

Dec 22, 2015, 00:00 by Engine Support

The Commission received an application from Dublin Airport to conduct a review the 2014 Determination. 

The Commission has come to the conclusion that there are no substantial grounds to conduct a review of the k factor as requested by Dublin Airport.

The Commission is of the view that there are substantial grounds to conduct an interim review of the 2014 Determination in order to possibly amend the runway trigger to better align remuneration with the reality of the timeline of the project.

In early 2016 the Commission will consult with all interested parties on the timing of the runway trigger.

Full details are in this document.

All documents relating to this decision and the 2014 Determination are here.